You've asked three companies to quote on a 250kW system for your site. One comes in noticeably cheaper per watt. On paper, the decision looks easy.
But on a commercial project, the cheapest quote is often the most expensive system you'll own. What's left out of a quote, and who stands behind it, matters far more than the headline number.
As a commercial solar specialist, we see this regularly. Businesses come to us after a low-cost system has stalled at network approval, underperformed, or been left without support. So here is an honest guide to comparing quotes properly, whoever you end up choosing.
Why price per watt misleads
Price per watt is useful for comparing residential systems, where the scope is fairly standard. On a 200kW+ commercial project, it hides almost everything that determines your return:
- Scope varies widely. One quote includes network application fees, protection relays, switchboard upgrades and structural certification. Another lists them as exclusions or "variations" to be priced later.
- Output matters more than size. Two 250kW systems can produce very different amounts of energy depending on layout, orientation, shading, inverter choice and design quality.
- Fit to your load decides savings. A system sized to your consumption pattern saves more than a bigger one that exports cheap power to the grid, or gets export-limited by the network.
- Lifetime costs aren't on the quote. Monitoring, maintenance, fault response and warranty support all affect what the system really costs over 25 years.
The better question is not "what does it cost per watt?" but "what will this system deliver, and who is responsible if it doesn't?"
Same site, two very different systems
Here's something most quotes never explain. A system designed for energy offset and a system designed for demand management can look completely different on the same site.
Designed for energy offset: the goal is to cut the kilowatt-hours you buy from the grid. That usually means a larger solar array that maximises daytime generation. It targets the usage charges on your bill and suits sites with steady daytime loads.
Designed for demand management: the goal is to cut the peaks that drive your demand charges. That often means a right-sized array paired with a battery. It targets the demand (kVA or kW) charges on your bill and suits sites with sharp peaks, such as compressors and machinery starting up.
Neither is "right" by default. Many sites need a mix of both. The right answer depends on your tariff, your load profile and what is actually driving your bill.
That's why we're solution-oriented, not product-oriented. We don't start with a panel count or a standard package. We start with the problem you need solved, then engineer the system that solves it. If a quote can't tell you which problem it's solving, it hasn't been designed for your business.
What to compare instead
Line the quotes up against these seven points. The gaps usually become obvious quickly.
1. What problem the system solves. Ask each installer whether the design targets energy offset, demand management or both, and why. The sizing should come from your actual interval meter data, not a rough estimate from your bill. Ask to see the load analysis and the expected self-consumption.
2. Realistic generation forecast. Look for a yearly output estimate in kilowatt-hours, with the assumptions shown. Be wary of savings figures with no workings behind them.
3. What's included, and what's not. Check for network application and studies, protection equipment, switchboard work, structural engineering, cranage, access equipment and commissioning. Read the exclusions carefully.
4. Who designs it. Ask whether the design is done by qualified engineers, and whether they will manage the distributor's questions and conditions.
5. Who installs it. Ask whether the company uses its own employed installers or subcontractors. It affects quality, safety, scheduling and who is accountable when something goes wrong.
6. Components and warranties. Compare panel, inverter and battery brands, and check who actually backs each warranty. A long warranty is only useful if a local, established company stands behind it.
7. Support after handover. Ask what monitoring is included, who watches it, how faults are reported and how quickly they are fixed. Ask for a maintenance plan and its cost.
Questions to ask every installer before you sign
Keep this list handy when you meet with suppliers. A confident specialist will answer every one without hesitation.
- Can you show me commercial projects of a similar size you've completed?
- Who will be on my site: your own employees or subcontractors?
- Who prepares and manages the network connection application?
- Is structural certification included in this price?
- What is excluded, and what could become a variation?
- How did you calculate the expected generation and savings?
- Who do I call if the system underperforms in year three?
- What monitoring and maintenance is included, and what does it cost after that?
If an answer is vague, or the response is "we'll sort that out later", treat it as a cost you haven't been quoted yet.
How we quote at RVB Energy
We won't always be the cheapest per watt, and we're upfront about why. Our quotes are built to be compared line by line:
- Designed by our in-house engineers from your real consumption data, with the generation forecast and assumptions shown
- Clear scope, including network approvals, protection, structural certification and commissioning, with exclusions spelled out
- Installed by our own crews, not subcontractors, so one team is accountable for quality and safety
- Backed by our after-sales team, who monitor generation and maintain the system for the long term
Commercial solar is a 25-year decision. We'd rather earn your trust with a transparent quote than win the job with a number that doesn't hold up.
Comparing quotes for a commercial solar or battery project? Send them through. We'll help you compare them honestly, and give you ours.